How Long Does a Kitchen Remodel Take in Amherst? A Week-by-Week Breakdown

How Long Does a Kitchen Remodel Take in Amherst? A Week-by-Week Breakdown

The most common question we hear after cost is timeline. How long will I be without a kitchen? When can I expect to be cooking again? The honest answer depends on scope, but there is a working framework for Amherst kitchen remodels that holds in most cases.

Pre-Construction: Weeks 1 Through 4

Before demo begins, four things need to happen: the permit is filed with the Town of Amherst Building Department, cabinets are ordered, countertop templating is scheduled for after cabinet install, and any material selections are finalized. Permit approval in Amherst typically runs 1 to 2 weeks. Semi-custom cabinet lead times run 4 to 6 weeks. The most common cause of kitchen remodel delays in the Northtowns is starting construction before cabinets are ready — demo proceeds, walls are opened, and then the project stalls waiting on materials. We order before demo.

Week 1: Demo and Rough-In

Demo typically takes 1 to 2 days for a standard Amherst kitchen. After demo, rough electrical and plumbing work begins. If the scope includes panel upgrades, new circuits for appliances, or plumbing relocations, a licensed electrician and plumber are on-site during this phase. Rough-in inspection with the Town of Amherst happens before walls close. This inspection usually runs 3 to 5 business days from request.

Pre-1970 homes in Amherst often reveal surprises during demo: knob-and-tube wiring, galvanized supply lines with restricted flow, and original drain lines that have partially failed. We photograph every finding and issue a written change order before addressing it. No verbal surprises.

Weeks 2 Through 3: Drywall and Prep

After rough-in inspection passes, drywall is hung, taped, and finished. This takes 3 to 5 days depending on the scope of wall work. Flooring installation follows drywall finish. If new tile or hardwood is in scope for the kitchen, it goes down before cabinet installation so the floor runs continuously under the toe kicks.

Weeks 3 Through 4: Cabinet Installation

Cabinet installation takes 1 to 3 days for a standard Amherst kitchen. Upper cabinets are hung first, then base cabinets. After cabinets are level and secured, the countertop fabricator comes on-site to template. Template-to-delivery for quartz or granite typically runs 7 to 10 business days in the WNY market.

Week 5: Countertops, Backsplash, and Fixtures

Countertops are delivered and installed in one day in most cases. Backsplash tile follows — 1 to 2 days for a standard tile install, plus 24 hours for grout cure before grouting, plus another 24 hours for sealer. Plumbing trim-out (sink, faucet, dishwasher reconnect) and electrical trim-out (outlets, switches, under-cabinet lighting) happen after countertops and backsplash are complete.

Week 6: Punch List and Final Inspection

Final electrical inspection with the Town of Amherst happens after all fixtures are installed. After inspection, appliances are delivered and installed. We walk the kitchen with you, generate a written punch list, and address items before the job is closed. Most Amherst kitchen remodels are fully complete in 5 to 6 weeks from demo date.

Midcity Handyman & Remodeling handles kitchen remodels throughout Amherst, Williamsville, Clarence, and the WNY Northtowns. We hold a New York State Home Improvement Contractor license and carry full insurance. Estimates are written, itemized, and include a project schedule with inspection milestones.

Call (833) 736-6647 or use the estimate form on this site to schedule a walkthrough.